Avon & Somerset Police HQ
The Project:
A multiple building headquarter campus spanning 22 acres.
The Challenge:
Updating an ageing site-wide BMS system to a leading edge, future-proof solution whilst ensuring that the current system’s operation and visibility remained complete and uninterrupted.
The Solution:
Survey, verification, testing and documentation of the BMS communications network. This enabled us to install additional network cabling in order to create a ‘mirror’ network that would allow the old and new systems to co-exist.
Offsite engineering of a new BMS to enable rapid changeover from the old system.
Phased replacement of the new BMS to ensure smooth and continuous operation.
Incorporation of a site-wide utility metering installation and energy monitoring programme.
Avon & Somerset Police HQ case study PDF